How do MEP firms plan workload when the deadlines are set by everyone except us?
We're a mid-size MEP consultancy, and at any given time each of our engineers is on something like six to ten projects. Fees per job are tight, so that's just the model. The catch is that almost none of the dates on those projects are ours. The architect sets the issue dates, the contractor pushes for early packages, the client changes the program, and we adjust.
Here's what happened a couple of weeks ago. Two architects on two unrelated projects both pulled their CD issue forward, one by a week, one by ten days. Separately, a third project had a late layout change that meant redoing a chunk of the mechanical. None of it was unusual on its own. But it all landed on the same week, on the same two senior engineers.
We didn't see it coming because our deadline tracker is a shared spreadsheet that each PM updates when they hear about a change. Some update it same day, some at the end of the week, some when reminded. Nobody was looking at it from the angle of what does Thursday look like for this person across all their jobs.
So we found out the usual way. Late nights, a couple of rushed sets, and one of those uncomfortable calls asking an architect for two more days.
I don't think there's a perfect fix, since we'll never control the upstream schedule. Are you tracking deadlines and workload in spreadsheets too or something else?